Friday, 2 August 2013

Sri Lanka is getting ready to battle against the power crisis

Kerawalapitiya Thermal Power Plant and Solar Power Generation in Hambanthota  
The power crisis is a major issue in the world especially in Third World countries. Alternative power generation is not an easy task for poorer countries due to the lack of technology and finance. Several Western countries have shifted from hydro to alternative power generation while Third World countries still depend on hydro power. Drafting a common mechanism to overcome the crisis is vital to address the power crisis. In addition to hydro power generation certain countries have focused on coal, wind and thermal power generation.

In the wake of averting a power crisis, Sri Lanka has also undertaken alternative power generation in addition to hydro power generation. The Norochcholai Lakvijaya coal power plant, the Puttalam wind power plant and the Kerawalapitiya Yugadanavi Thermal power plant assists national power generation considerably. Meanwhile, the Government has implemented several major and small hydro power projects at suitable locations. The Upper Kotmale project takes significance. The Puttalam district is an appropriate location for wind power generation. The wind power plants in the Puttalam district adds 50 MW of electricity to the national grid alone, Wind Post Private Limited has invested Rs. 4,000 million on the project.

Wind power plants have been set up in locations where the wind velocity is high. These areas receive less rainfall compared to other parts of the country. Rainfall accompanied by wind in these areas will not affect electricity generation. In the event these areas experience heavy rain, power generation will decline if heavy rains continue. There will be a steady drop in electricity generation.

Three wind power plants - the Powerjeng, Nirmalapura and Daily Life Renewable Energy (DLRE) function in various locations in the district under the same company. The project was started in 2011. Seguwanq and the Widathamuni plants add 20 MW of electricity to the national grid. There are 12 towers in Seguwanq plant and 13 towers in the Widathamuni plant. The maximum electricity generation capacity from each tower will be 800 kilowatts. There is a general structure to maintain the functioning of the towers and to detect faults.

Norochcholai  Coal Power Plant and Wind Power Generating Towers in Hambanthota
The increase or drop of power generation depends on wind velocity. The Nirmalapura wind power plant is in Karamba and the Daily life Renewable Energy (DLRE) generate 20 MW of electricity, each 10 MW. The Wind Post Private Limited also plans to set up a 20 MW electricity generation plant in Elephant-Pass. In the case of wind power. There is no excess expenditure except for the cost of setting up equipment and the towers. The wind power plants in the Puttalam district contribute to 30 percent.

During the high wind season, the electricity generation capacity will be high. Electricity generation will be high between May to August and low between September to November. The shortage will be balanced by excess generation of electricity when the wids are ate high velocity. Although wind power plants have relatively little impact on the environment, compared to fossil fuel power plants, there is some concern over the noise produced by the rotor blades, aesthetic (visual) impacts and birds and bats being killed by flying into the rotors. Most of these problems have been resolved or greatly reduced through technological development or by proper sitting of wind plants.

Meanwhile, Norochcholai coal power plant also contributes to the National Grid. Under the first phase, 300 MW of electricity and under the second phase 600 MW was added Ministry sources said. Plans are afoot to add 900 MW of electricity to the national grid by the end of this year, according to Power and Energy Ministry sources. The Norochcholai Coal power plant was financed by the Chinese Government. US$ 455 million was spent for the first phase and US$ 891 million was spent for the second phase.

The Government of Sri Lanka spent Rs. 5,300 million for the first phase and Rs.11,000 million for the second phase, sources said. A jetty have been constructed with all facilities to ease the unloading of coal. Two giant cranes have been set up to expedite the unloading of coal, the sources said. The sources said that 114 metric tons of coal is used for one hour to generate electricity. An environment-friendly coal yard has been constructed in the plant premises to ensure the protection of biodiversity and the environment.

Coal required for three months can be stored in the yard. Coal with less sulfur content is imported from Indonesia. A 117 kilometre- long 220 MW high tension line has been set up from the plant to Veyangoda under the first phase to add to the national grid. Under the second phase two turbines were set up and 300 MW electricity was added to the national grid. A 100 kilometre long 220 MW high tension line was set up from Norachcholai to Anuradhapura. A sub station has been set up at Dummalasooriya, Chilaw. Environment damage has been minimised in this instance. Mobile teams also operate in the region to assess the changes taking place in the environment and biodiversity changes to minimise the hazards.